Two major London train stations closed from today for £20 million works

Two major London stations have been shut for three weeks as part of a £20 million upgrade, with commuters warned to expect disruption.

Work to replace nearly 2km of track, rebuild sections of platform and carry out repairs to the Hungerford and Waterloo East pedestrian links was already underway on Sunday, July 26.

Work to replace nearly 2 km of track is underway

Network Rail

The closures will affect Southeastern services, with trains that normally run into Charing Cross being diverted instead to London Victoria, London Cannon Street and London Blackfriars.

Some services will also terminate at London Bridge.

Passengers are being urged to check their route before travelling, as alternative services will be in place throughout the closure.

Here’s everything we know about the works…

When are the stations closing?

The main closures will last 22 days, from Sunday, July 26, to Sunday, August 16, to coincide with the summer holidays.

But there will also be additional weekend closures before and after for preparation and follow-up work:

  • Saturday, July 18
  • Sunday, July 19
  • Saturday, August 22
  • Sunday, August 23
  • Saturday, October 10
  • Sunday, October 11

Network Rail has warned that travel arrangements on these extra closure dates may be different from the main 22-day closure, so passengers should check before setting off.

Why are Charing Cross and Waterloo East closing?

The stations are closed to allow engineers to carry out a major £20million upgrade of the railway between them.

The work includes replacing around 1,800 metres of track and installing 16 new sets of switches and crossings — the equipment that allows trains to move between different tracks.

The new infrastructure will replace equipment that has been in place since 1990, which Network Rail says will help to improve reliability and keep journeys running smoothly.

At Waterloo East, track drainage will also be upgraded to help maintain track quality and allow trains to continue running safely at full line speed.

Meanwhile, parts of Charing Cross station are being rebuilt, with new foundations and surfaces installed at the country end of the platforms to keep them safe and accessible for passengers.

Structural repairs are also being carried out on the 175-year-old Hungerford Bridge, which takes the railway over the Thames, and the pedestrian link bridge between Waterloo East and London Waterloo.

The work will keep the structures open for decades ahead, Network Rail says.

What are the likely disruptions?

No trains will call at London Charing Cross or Waterloo East while work is carried out.

Instead, Southeastern services will be diverted to London Victoria, Cannon Street, Blackfriars, and London Bridge.

Southeastern has warned passengers to expect delays and cancellations.

Can I get a refund for pre-booked trains?

Passengers affected by the closures can claim a refund for all ticket types, including journeys made using reasonable alternative routes.

Southeastern has set up a dedicated refund form, which is available on the Southeastern website.

Scott Brightwell, the train services director on the Southeastern Railway, said, “The £20 million investment we are delivering will see 1990s track and platforms upgraded to make journeys safer and more reliable, and Victorian-era structures strengthened to remain fit for the future.

“By consolidating the work into a 22‑day closure, supported by preparation and follow‑up weekends, we can complete the work more quickly and with less disruption overall than the alternative options of 60 weekend closures or four to five 9‑day closures.

He added: “We have planned the closure for the summer, when passenger numbers are around 20 per cent lower and schools are closed, to help manage the impact on customers.”

Make sure our latest headlines always appear at the top of your Google searches by adding us as a favourite source. Click here to activate. Or add us as your preferred source to your Google Search settings



Source link

Hot this week

Premier League Clubs Complete Final Pre-Season Preparations Ahead of 2026/27 Kick-Off

Premier League Clubs Complete Final Pre-Season Preparations Premier League pre-season...

UK Wildfires Latest: What’s Happening on 15 August 2026

The UK wildfires' latest update for 15 August 2026...

MP calls on Andy Burnham to offer railcard discount for commuters over 30

An MP has urged ministers serving Andy Burnham to...

LIV Golf Michigan Tickets No Longer on Sale as Team Championship Faces Cancellation Reports

LIV Golf Michigan Tickets No Longer on Sale LIV Golf...

Two Seriously Injured as Train Derails Near Lewes and Carriages Topple Sideways

Lewes Train Derailment Leaves Two Seriously Injured The Lewes train...

Topics

Premier League Clubs Complete Final Pre-Season Preparations Ahead of 2026/27 Kick-Off

Premier League Clubs Complete Final Pre-Season Preparations Premier League pre-season...

UK Wildfires Latest: What’s Happening on 15 August 2026

The UK wildfires' latest update for 15 August 2026...

MP calls on Andy Burnham to offer railcard discount for commuters over 30

An MP has urged ministers serving Andy Burnham to...

Two Seriously Injured as Train Derails Near Lewes and Carriages Topple Sideways

Lewes Train Derailment Leaves Two Seriously Injured The Lewes train...

Emirates SkyCargo Transports Orbitworks’ Altair-1 Satellite in Major UAE Space Mission

Emirates SkyCargo Transports Altair-1 Emirates SkyCargo transports Altair-1, the satellite...

All the Fringe Candidates Fighting Nigel Farage in Clacton By-Election

The fringe candidates fighting Nigel Farage in the Clacton...

Banning zero-hours contracts could cost businesses up to £3bn a year

Banning zero-hours contracts could cost businesses up to £3bn...
spot_img

Related Articles

Popular Categories

spot_imgspot_img